Examlex

Solved

The Most Pessimistic Time for a Task Is 28 Days

question 76

Multiple Choice

The most pessimistic time for a task is 28 days.The most optimistic time for the same task is one fourth of the pessimistic time.Calculate the variance for the duration of the activity.