If the most optimistic time for completing an activity is 14,the most likely time is 16,and the most pessimistic time is 30,then the estimated time for the activity is ______.


Definitions:

Total Construction Cost

The complete financial expenditure involved in constructing a building or infrastructure, encompassing material, labor, equipment, and indirect costs.

Operating Cost

Refers to the ongoing expenses associated with the running of a business, such as utilities, rent, payroll, and maintenance.

Location Decision

The process of selecting a geographical location for a company’s operations, facilities, or investments, considering factors such as cost, accessibility, and legal requirements.

Linear Programming

A mathematical method used to find the best possible outcome or solution from a given set of parameters or list of requirements, subject to certain constraints.