An Activity X Has a Duration of 5 Weeks and Is

question 88

Multiple Choice

An Activity X has a duration of 5 weeks and is budgeted to cost $12,000.The crash time for this activity is 3 weeks and is expected to cost $32,000.The cost slope for Activity X is given by ______.