An assembly line to be balanced has six tasks in precedence.The task times are shown in the following table.Based on demand forecasts,the output rate has to be 160 units per day.The line operates 8 hours a day.Calculate the desired cycle time C.
 Tasks  lmmediate Predecessor  Task Time in Minutes  A  NONE 3 B  A 1 C  A 2 D B,C3 E C3 F D,E2\begin{array} { | l | l | l | } \hline \text { Tasks } & \text { lmmediate Predecessor } & \text { Task Time in Minutes } \\\\\hline \text { A } & \text { NONE } & 3 \\\hline \text { B } & \text { A } & 1 \\\hline \text { C } & \text { A } & 2 \\\hline \text { D } & \mathrm { B } , \mathrm { C } & 3 \\\hline \text { E } & \mathrm { C } & 3 \\\hline \text { F } & \mathrm { D } , \mathrm { E } & 2 \\\hline\end{array}


Definitions:

Illegal

Actions or activities that are forbidden by law.

Moral Development

The formation of an individual's understanding and sense of right and wrong, influencing their behavior and attitudes.

Postconventional

A level of moral reasoning in Kohlberg's theory characterized by the individual's ability to think beyond societal norms and consider universal ethical principles.

Belief System

A Belief System is a set of principles or tenets that form the basis of a person's convictions, values, or actions.

Related Questions