In Agile Projects,overall Planning Is at a High Level,and Only

question 48

Multiple Choice

In agile projects,overall planning is at a high level,and only the near-term work is planned in detail.The project work is conducted in iterations (sprints) that are normally: 


Definitions:

Critical Path

Identifies the longest sequence of dependent tasks in a project, determining the shortest possible duration to complete the project.

Gantt Chart

A visual tool in project management that displays a project schedule, showing the start and finish dates of elements and dependencies.

PERT Chart

A graphical tool used in project management to schedule, organize, and coordinate tasks within a project.

Early Start Dates

The earliest possible point in time when the activities of a project can begin, taking into account all constraints and preceding tasks.