The Work Breakdown Structure (WBS)is Normally Developed by Listing Deliverables

question 42

True/False

The Work Breakdown Structure (WBS)is normally developed by listing deliverables - major deliverables first and then progressively smaller ones until the team feels that every deliverable has been identified.