A _______ Is the Approved Project Plan Mainly Consisting of Scope,schedule,and

question 27

Multiple Choice

A _______ is the approved project plan mainly consisting of scope,schedule,and cost that is not normally altered unless a  formal change control request is approved for modifying these plans.​ 