Crashing Is a Project Schedule Compression Technique That Expedites a Project

question 40

True/False

Crashing is a project schedule compression technique that expedites a project by executing activities at the same time that ordinarily would be done one after the other.


Definitions:

FOB Point

A shipping term indicating the point at which the ownership and risk related to goods are transferred from seller to buyer, defined in terms of location.

Legal Title

A formal recognition of ownership of property or assets which includes the rights to use, sell, or control the said property or assets.

Containers On Flatcars (COFC)

A type of intermodal freight transport where shipping containers are carried on railroad flatcars for part of their journey.

Trailers On Flatcars (TOFC)

A freight system where trailers are transported on railway flatcars, combining road and rail transportation.