The anticipated amount of time which will elapse before a particular project or activity is completed.
Critical Path
The critical path is the longest sequence of activities in a project plan that must be completed on time for the project to finish by its due date.
Activity Variance
The difference between the expected performance or cost of an activity and its actual performance or cost.
Preceding Activity
In project management, an activity that must be completed before a subsequent activity can begin.
Q32: List and explain the three sources that
Q37: How many stages of the jury selection
Q64: Reporting to a probation officer is an
Q70: Which of the following is a type
Q92: You are a detective in a major
Q104: The introduction of victim impact statements has
Q107: A surety is an individual who will
Q126: Which of the following is the basis
Q128: Which of the following is a basic
Q135: Studies of the provincial courts across Canada