Examlex

Solved

The City of Oak Park Constructed a New Storage Facility

question 19

Multiple Choice

The City of Oak Park constructed a new storage facility using the city's own public works employees. Construction costs were incurred in the amount of $900,000, plus $25,000 in interest on short-term notes used to finance construction. What amount should be capitalized in the government-wide statements?


Definitions: