Using the Power-Interest Grid,match Up These Two Dimensions of Stakeholders

question 19

Short Answer

Using the Power-Interest Grid,match up these two dimensions of stakeholders with the appropriate relationship with the project manager.
A)Low power,low interest
B)High power,low interest
C)High interest,low power
D)High interest,high power
1)Monitor
2)Keep informed
3)Closely manage
4)Keep satisfied


Definitions:

Time Lines

Graphical representations used in project management and planning to illustrate the schedule and sequence of tasks or events.

Time Value

The principle that having money now is preferable to receiving the same sum later on, as it has greater earning potential.

Graphic Portrayal

Graphic portrayal involves the visual representation of data or concepts, using charts, graphs, or other graphical tools to illustrate relationships and trends.

Interest Rate

The proportion of a loan that is charged as interest to the borrower, typically expressed as an annual percentage.

Related Questions