question 11

Short Answer

Following is a list of a few of the more important aspects of the transition from project to integrated operation that must be considered when the project functions are distributed.Match each one with its description.
A)Personnel
B)Manufacturing
C)Accounting / finance
D)Engineering
1)Where will the project team go?
2)Have the project accounts been closed and audited? Do the new department budgets include the additional work needed by the project?
3)Are all drawings complete and on file? Are operating manuals and change procedures understood?
4)Is training complete? Are input materials and the required facilities available? Does the production system layout have to be replanned?


Definitions:

World Price

The international market price of a good, influenced by global supply and demand conditions.

Hypothetical Nations

Hypothetical nations are theoretical or imaginary countries used for the purpose of discussion, analysis, or illustration in economic or political scenarios.

Excise Tax

A tax on specific goods, such as alcohol and tobacco, often levied at the manufacturing level.

Imported Good

A product or service that is brought into one country from another, making it available for domestic consumption or use.

Related Questions