You Have Collected the Data for a Time-Cost CPM Scheduling

question 56

Multiple Choice

You have collected the data for a Time-Cost CPM Scheduling model analysis.The time is in days and the project "direct costs" are given below.
The indirect costs for the project are determined on a daily duration basis.If the project lasts 16 days the total indirect costs are $400,15 days they will be $250,14 days they will be $200,and 13 days they will be $100.If you crash this project by one day what is the total (i.e. ,direct and indirect) project cost?
You have collected the data for a Time-Cost CPM Scheduling model analysis.The time is in days and the project  direct costs  are given below. The indirect costs for the project are determined on a daily duration basis.If the project lasts 16 days the total indirect costs are $400,15 days they will be $250,14 days they will be $200,and 13 days they will be $100.If you crash this project by one day what is the total (i.e. ,direct and indirect) project cost?   A) $2,150 B) $2,300 C) $2,400 D) $2,450 E) $2,500


Definitions:

Abilities of Resources

The skills, knowledge, and competencies that economic resources like labor, capital, and land possess.

Barter

The trade of goods or services among individuals without employing money as a means of transaction.

Desk

A piece of furniture with a flat top and legs, used for writing, working or using a computer.

Box of Tools

Metaphorically refers to a set of skills, strategies, or resources available to individuals or organizations for performing tasks or solving problems.

Related Questions