Use This Scenario for the Following Question(s) -Refer to the Scenario Above

question 100

Multiple Choice

Use this scenario for the following question(s) .
The process design team at a manufacturer has broken an assembly process into eight basic steps, each with a required time, and predecessor as shown in the table. There are 7.5 productive hours available in a day and the manufacturer wishes to produce 400 units. Balance the line by assigning tasks to workstations to fill up as much takt time as possible. Break ties by assigning the longest task first.
 Task  Time (sec)  Predecessor  A 45 B 50 A  C 20 A  D 55 A  E 15 D  F 65 D  G 25 E  H 35 B, C, F, G \begin{array} { | c | c | c | } \hline \text { Task } & \text { Time } ( \mathrm { sec } ) & \text { Predecessor } \\\hline \text { A } & 45 & \cdots \\\hline \text { B } & 50 & \text { A } \\\hline \text { C } & 20 & \text { A } \\\hline \text { D } & 55 & \text { A } \\\hline \text { E } & 15 & \text { D } \\\hline \text { F } & 65 & \text { D } \\\hline \text { G } & 25 & \text { E } \\\hline \text { H } & 35 & \text { B, C, F, G } \\\hline\end{array}
-Refer to the scenario above. What task(s) should be assigned at the third workstation?


Definitions:

Boredom

A state of feeling disinterested in one's surroundings, activities, or responsibilities.

Communicator

An individual or entity that conveys information or messages to others through various mediums.

Message

A piece of information or communication sent from one individual or group to another.

Context

The circumstances or setting surrounding an event, statement, or idea which gives it additional meaning.

Related Questions