Use This Scenario for the Following Question(s) -Refer to the Scenario Above

question 66

Multiple Choice

Use this scenario for the following question(s) .
The process design team at a manufacturer has broken an assembly process into eight basic steps, each with a required time, and predecessor as shown in the table. There are 7.5 productive hours available in a day and the manufacturer wishes to produce 400 units. Balance the line by assigning tasks to workstations to fill up as much takt time as possible. Break ties by assigning the longest task first.
 Task  Time (sec)  Predecessor  A 45 B 50 A  C 20 A  D 55 A  E 15 D  F 65 D  G 25 E  H 35 B, C, F, G \begin{array} { | c | c | c | } \hline \text { Task } & \text { Time } ( \mathrm { sec } ) & \text { Predecessor } \\\hline \text { A } & 45 & \cdots \\\hline \text { B } & 50 & \text { A } \\\hline \text { C } & 20 & \text { A } \\\hline \text { D } & 55 & \text { A } \\\hline \text { E } & 15 & \text { D } \\\hline \text { F } & 65 & \text { D } \\\hline \text { G } & 25 & \text { E } \\\hline \text { H } & 35 & \text { B, C, F, G } \\\hline\end{array}
-Refer to the scenario above. What is the theoretical minimum number of stations that will be used if the line is balanced using the appropriate takt time?


Definitions:

Intelligent Parenting

An approach to parenting that emphasizes awareness, education, and emotional intelligence aiming to foster healthy development in children.

Multitasking

The act of handling more than one task simultaneously, often requiring switching focus quickly between tasks.

Selective Optimization

A strategy focusing on maximizing development in certain areas while minimizing losses in others, often used to manage aging or resource allocation.

Decade

A period of ten years.

Related Questions