Use This Scenario for the Following Questions

question 20

Multiple Choice

Use this scenario for the following questions.
The process design team at a manufacturer has broken an assembly process into eight basic steps, each with a required time, and predecessor as shown in the table. There are 7.5 productive hours available in a day and the manufacturer wishes to produce 400 units. Balance the line by assigning tasks to workstations to fill up as much takt time as possible. Break ties by assigning the longest task first.
Use this scenario for the following questions. The process design team at a manufacturer has broken an assembly process into eight basic steps, each with a required time, and predecessor as shown in the table. There are 7.5 productive hours available in a day and the manufacturer wishes to produce 400 units. Balance the line by assigning tasks to workstations to fill up as much takt time as possible. Break ties by assigning the longest task first.    -Refer to the scenario above.How many workers must be added to increase the output rate to one unit per minute? A)  1 B)  2 C)  3 D)  4
-Refer to the scenario above.How many workers must be added to increase the output rate to one unit per minute?


Definitions:

Unlikely

Having a low probability of occurring; not likely to happen.

Attitude Stability

The degree to which an individual's attitudes, opinions, and beliefs remain consistent over time, despite external factors or influences.

Environment

The environment encompasses all external factors and conditions that surround and affect living organisms, including natural, social, and built aspects.

Attitudes

Psychological tendencies expressed by evaluating a particular entity with some degree of favor or disfavor.

Related Questions