This Gantt Chart Can Be Used to Show

question 71

Multiple Choice

This Gantt chart can be used to show: This Gantt chart can be used to show:   A)  activity D must come before activity C. B)  activity F can be done at the same time as D. C)  activity E can begin as soon as activity A is complete. D)  activities D and B can be done simultaneously.