What is the latest that activity B can start if A lasts 35 days,B lasts 5,days C lasts 6 days,and D lasts 7 days? What is the latest that activity B can start if A lasts 35 days,B lasts 5,days C lasts 6 days,and D lasts 7 days?   A)  35 B)  36 C)  40 D)  41