A Seven Activity Project Has the Activity Durations (In Weeks)and

question 38

Multiple Choice

A seven activity project has the activity durations (in weeks) and costs shown in the table.It is possible to speed up every one of the activities by paying a little more.What is the least expensive 30-week project? A seven activity project has the activity durations (in weeks) and costs shown in the table.It is possible to speed up every one of the activities by paying a little more.What is the least expensive 30-week project?   A)  $18,900 B)  $19,200 C)  $19,500 D)  $19,800