The Overall Consequence of Failure Was 0

question 58

Multiple Choice

The overall consequence of failure was 0.4 and curiously enough,the consequence of performance is twice that of reliability;the consequence of reliability is twice that of schedule;and the consequence of schedule is twice that of cost.What is the consequence of failure cost?