What Is the Earliest That Activity D Can Begin If

question 13

Multiple Choice

  What is the earliest that Activity D can begin if Activity A takes 3 days,Activity B takes 5 days,and Activity C takes 7 days? A) Day 15 B) Day 7 C) Day 5 D) Day 3 What is the earliest that Activity D can begin if Activity A takes 3 days,Activity B takes 5 days,and Activity C takes 7 days?