What Is the Late Finish Time for Activity D Given

question 83

Multiple Choice

What is the late finish time for Activity D given the activity times and precedence requirements shown in the table?  Activity  Time  Predecessor  A 5B7C8 A D7 A E4 BF8C,DG9E,FH7G\begin{array} { | l | l | l | } \hline \text { Activity } & \text { Time } & \text { Predecessor } \\\hline \text { A } & 5 & -- \\\hline B & 7 & -- \\\hline \mathrm { C } & 8 & \text { A } \\\hline \mathrm { D } & 7 & \text { A } \\\hline \mathrm { E } & 4 & \mathrm {~B} \\\hline \mathrm { F } & 8 & \mathrm { C } , \mathrm { D } \\\hline \mathrm { G } & \mathrm { 9 } & \mathrm { E } , \mathrm { F } \\\hline \mathrm { H } & 7 & \mathrm { G } \\\hline\end{array}


Definitions:

Low-Cost

Describes products or services offered at a price lower than the market average to attract cost-sensitive consumers.

Differentiation

Relates to distinguishing or creating differences between products, services, or organizational entities to create a competitive advantage.

Strategic Choice

Refers to the decisions that determine the direction of an organization's long-term goals and the means to achieve them.

Competitive Advantage

The attributes or conditions that enable a company to outperform its competitors, such as superior quality, innovative technology, or cost efficiency.

Related Questions