-Use the Network Diagram and Activity Lengths in the Nodes

question 96

Multiple Choice

  -Use the network diagram and activity lengths in the nodes to determine the late start time for activity F. A) 21 B) 24 C) 26 D) 23
-Use the network diagram and activity lengths in the nodes to determine the late start time for activity F.


Definitions: