-Use the Network Diagram and Activity Lengths in the Nodes

question 64

Multiple Choice

  -Use the network diagram and activity lengths in the nodes to determine the late finish time for activity C. A) 12 B) 13 C) 14 D) 15
-Use the network diagram and activity lengths in the nodes to determine the late finish time for activity C.