Use the Values in the Table to Calculate Activity Durations

question 4

Essay

Use the values in the table to calculate activity durations and variances for the project.Which path is critical? How closely should the other path be watched and why?
 Activity  Predecessor  Optirnistic  Likely  Pessimistic  A 5710B A 469C A 101318DB31115EC,D235\begin{array} { | l | l | l | l | l |} \hline \text { Activity } & \text { Predecessor } & \text { Optirnistic } & \text { Likely } & \text { Pessimistic } \\\hline \text { A } & -- & 5 & 7 & 10 \\\hline B & \text { A } & 4 & 6 & 9 \\\hline \mathrm { C } & \text { A } & 10 & 13 & 18 \\\hline \mathrm { D } & \mathrm { B } & 3 & 11 & 15 \\\hline \mathrm { E } & \mathrm { C } , \mathrm { D } & 2 & \boldsymbol { 3 } & 5 \\\hline\end{array}

Identify and describe common and uncommon inventory costing assumptions.
Evaluate the practicality and implications of different inventory methods on business operations.
Understand the effect of inventory costing decisions on gross profit calculation.
Analyze the influence of inventory costing methods on tax liabilities.

Definitions:

Plasma Membrane

Acting as a regulatory boundary, the plasma membrane delineates the cell's internal environment from the external world, overseeing the transport of substances into and out of the cell.

Interneurons

Neurons that transmit signals between sensory and motor neurons, playing critical roles in reflexes and neuronal circuits.

Central Nervous System

Part of the nervous system consisting of the brain and spinal cord, responsible for processing information and coordinating activity throughout the body.

Myelin Sheath

The white, fatty material that forms a sheath around the axons of certain nerve cells, which are then called myelinated fibers.

Related Questions