-Use the Network Diagram and Activity Lengths in the Nodes

question 53

Multiple Choice

  -Use the network diagram and activity lengths in the nodes to determine the early finish time for activity G. A) 26 B) 25 C) 24 D) 23
-Use the network diagram and activity lengths in the nodes to determine the early finish time for activity G.


Definitions: