What Is the Slack Time for Activity B Given the Activity

question 16

Multiple Choice

What is the slack time for Activity B given the activity times and precedence requirements shown in the table?  Activity  Time  Predecessor A5B7C8 A D7 AE4 BF8C,DG9E,FH7G\begin{array} { | l | l | l | } \hline \text { Activity } & \text { Time } & \text { Predecessor } \\\hline \mathrm { A } & 5 & - - \\\hline \mathrm {B} & 7 &- - \\\hline \mathrm { C } & 8 & \text { A } \\\hline \mathrm { D } & 7 & \mathrm {~A} \\\hline \mathrm { E } & 4 & \mathrm {~B} \\\hline \mathrm { F } & 8 & \mathrm { C } , \mathrm { D } \\\hline \mathrm { G } & 9 & \mathrm { E } , \mathrm { F } \\\hline \mathrm { H } & 7 & \mathrm { G } \\\hline\end{array}


Definitions:

Effective Self-Talk

The practice of guiding one's thoughts in a positive and constructive manner to enhance confidence and performance.

Childhood Events

Refers to significant incidents or experiences that occur during a person's early years, influencing their development and personality.

Self-Concept

The awareness or perception of oneself derived from the beliefs, attitudes, and values an individual holds about their abilities, appearance, and personality.

Organization's Progress

The advancement or growth of a company or institution towards achieving its goals and improving its operations.

Related Questions