An Activity Performed by a Subcontractor Is Scheduled for 20

question 55

Multiple Choice

An activity performed by a subcontractor is scheduled for 20 weeks at an anticipated cost of $100,000.Due to slippage on the critical path you need to reduce this activity by three weeks.If the subcontractor informs you that the activity can be completed in 16 weeks for $200,000,what is the slope for the activity?


Definitions:

Diversity of Citizenship

A basis for federal court jurisdiction when parties in a lawsuit are citizens of different states or a foreign country, allowing for disputes to be heard in federal court.

Citizens

Members of a state or nation who are legally recognized and entitled to its protection and to political rights.

Different States

Variations across U.S. states or countries, particularly concerning laws, regulations, and cultural practices.

Diversity of Citizenship

A legal principle allowing the federal courts in the United States to hear cases where the parties are citizens of different states or a foreign country.

Related Questions