question 17
Multiple Choice
A project has the activity duration and cost information indicated in the table where all times are in weeks.What is the lowest total cost for completing this project in 35 days? Activity A B C DEFGHJ Predecessor −− A A B C EDAH Normal Time 812153978126 Normal Cost $12,000$18,000$22,000$9,000$15,000$5,000$13,000$20,000$45,000 Crash Time 599255684 Crash Cost $22,000$32,000$62,000$18,000$35,000$8,000$23,000$32,000$56,000