A Project Consists of Six Consecutive Tasks That Have Average

question 98

Multiple Choice

A project consists of six consecutive tasks that have average duration and worst-case duration estimates (in weeks) as shown in the table.Use Newbold's method to determine the aggregated two sigma buffer for this project.  Activity  Average  Worst-Case A1014B24C612D813.5E912F575\begin{array} { | l | l | l | } \hline \text { Activity } & \text { Average } & \text { Worst-Case } \\\hline \mathrm { A } & 10 & 14 \\\hline \mathrm { B }& 2 & 4 \\\hline \mathrm { C } & 6 & 12 \\\hline \mathrm { D } & 8 & 13.5 \\\hline \mathrm { E } & 9 & 12 \\\hline \mathrm { F } & 5 & 75 \\\hline\end{array}


Definitions:

Wye-Connected

A method of connecting three-phase motors and generators where the end of each of the three coils is connected to form a 'Y' shape, also known as a star connection.

Line Voltage

The voltage present in the electrical power transmission lines available for end users or machinery.

Phase Voltage

The voltage measured in a single phase of a multi-phase system, often used in the analysis of electrical power distribution.

Square Root

The value that, when multiplied by itself, gives the original number. It is often represented by the radical symbol √.

Related Questions