A Project Is Represented by the Activity Durations (Estimated at 90

question 92

Multiple Choice

A project is represented by the activity durations (estimated at 90% likelihood of completion) and precedence requirements shown in the table.What is the length of the project buffer if this project is managed using critical chain methodology?  Activity  Predecessor  Ieength  Activity  Predecesser  Ieength  A 20DB16B A 20EC8C A 10 FD,E8\begin{array} { | l | l | l | l | l | l | } \hline \text { Activity } & \text { Predecessor } & \text { Ieength } & \text { Activity } & \text { Predecesser } & \text { Ieength } \\\hline \text { A } & - - & 20 & \mathrm { D } & \mathrm { B } & 16 \\\hline \mathrm { B } & \text { A } & 20 & \mathrm { E } & \mathrm { C } & 8 \\\hline \mathrm { C } & \text { A } & 10 & \mathrm {~F} & \mathrm { D } , \mathrm { E } & 8 \\\hline\end{array}


Definitions:

Narcissism

A psychological condition characterized by self-centeredness, a high need for admiration, and a lack of empathy for others.

Conscientiousness

A personality trait characterized by organization, dependability, and a strong sense of duty.

Leadership Substitutes

Factors in a workplace that reduce the need for a leader or make traditional leadership ineffective.

Unnecessary

Not needed or essential; something that could be omitted without any loss of functionality or value.

Related Questions