A Project Consists of Four Activities with Information as Shown

question 84

Multiple Choice

A project consists of four activities with information as shown in the table.What is the overall standard deviation of the project's duration?  Standard  Activity  Predecessor  Length  Deviation  A 102 B  A 123 C  A 162 D B,C143\begin{array}{|l|l|l|l|}\hline&&&\text { Standard }\\ \text { Activity } & \text { Predecessor } & \text { Length } & \begin{array}{l}\text { Deviation }\end{array} \\\hline \text { A } & - & 10 & 2 \\\hline \text { B } & \text { A } & 12 & 3 \\\hline \text { C } & \text { A } & 16 & 2 \\\hline \text { D } & \text {B,C} & 14 & 3\\\hline \end{array}


Definitions:

Psychological Questions

Inquiries that delve into an individual's mental, emotional, and behavioral state, aimed at understanding their psychological health and well-being.

Psychologists

Professionals specializing in the study and treatment of the mind and behavior, exploring how people think, feel, and interact.

Cognitive Psychologists

Scientists who study mental processes such as perception, memory, thought, and problem-solving.

Evolutionary Psychologist

A specialist who studies how evolutionary principles help explain the structure and function of the human mind and behavior.

Related Questions