Create a Resource Loading Chart Using Early Start Times for the Project

question 28

Essay

Create a resource loading chart using early start times for the project described by this table.
 Activity  Tirne  Predecessor  Task A144B25C4 A5D9 B4E8C5F2C3G3D2H5 F,G4K1E3L13H, K4\begin{array} { | l | l | l | l |} \hline \text { Activity } & \text { Tirne } & \text { Predecessor } & \text { Task } \\\hline \mathrm { A } & 14 & - & 4 \\\hline \mathrm { B} & 2 & - & 5 \\\hline \mathrm { C } & 4 & \mathrm {~A} & 5 \\\hline \mathrm { D } & 9 & \mathrm {~B} & 4 \\\hline \mathrm { E } & 8 & \mathrm { C } & 5 \\\hline \mathrm { F } & 2 & \mathrm { C } & 3 \\\hline \mathrm { G } & \mathbf { 3 } & \mathrm { D } & 2 \\\hline \mathrm { H } & 5 & \mathrm {~F}, \mathrm { G } & 4 \\\hline \mathrm { K } & 1 & \mathrm { E } & 3 \\\hline \mathrm { L } & 13 & \mathrm { H } , \mathrm {~K} & 4 \\\hline\end{array}


Definitions:

Mission Statement

A written declaration of an organization's core purpose and focus that normally remains unchanged over time.

Existence

The state or fact of being real, present, or alive.

Related Questions