Consider the Project That Is Neatly Summarized in This Table

question 80

Multiple Choice

Consider the project that is neatly summarized in this table.What is the top priority activity when using the most successors leveling heuristic?  Activity  Duration  Predecessors  Workers Required A23B4 A 4C6 A 2D7 B5E9C,D2E2\begin{array} { | l | l | l | l | } \hline\text { Activity } & \text { Duration } & \text { Predecessors } & \text { Workers Required } \\\hline \mathrm { A } & 2 & - & 3 \\ \hline \mathrm { B} & 4 & \text { A } & 4 \\\hline \mathrm { C } & 6 & \text { A } & 2 \\\hline \mathrm { D } & 7 & \mathrm {~B} & 5 \\\hline \mathrm { E } & 9 & \mathrm { C } , \mathrm { D } _ { 2 } \mathrm { E } & 2 \\\hline \end{array}