The Project Described in the Table Uses the Same Resource

question 4

Multiple Choice

The project described in the table uses the same resource for activities A,B,C,and D.Which activity gets first use of this resource if we assign the resource based on the activity with the smallest amount of slack?  Dctivity  Duration  Predecesser  WBS ID  W 412 A 3 W 16B4 W 15C5 W 13D6 W 14E1 B17Z1 A,E,C,D18\begin{array} { | l | l | l | l | } \hline \text { Dctivity } & \text { Duration } & \text { Predecesser } & \text { WBS ID } \\\hline \text { W } & 4 & - - & 12 \\\hline \text { A } & 3 & \text { W } & 16 \\\hline B & 4 & \text { W } & 15 \\\hline \mathrm { C } & 5 & \text { W } & 13 \\\hline \mathrm { D } & 6 & \text { W } & 14 \\\hline \mathrm { E } & 1 & \mathrm {~B} & 17 \\\hline \mathrm { Z } & 1 & \mathrm {~A} , \mathrm { E } , \mathrm { C } , \mathrm { D } & 18 \\\hline\end{array}


Definitions: