Use the Project Described in the Table to Determine the Total

question 10

Multiple Choice

Use the project described in the table to determine the total resources required for activity D if a worker is expected to work half-time (four hours per day) on this project.  Activity  Duration  Predecessor  A 5 days B4 days  A C5 days  A D6 days BE6 days C,DF6 days E\begin{array} { | l | l | l| } \hline \text { Activity } & \text { Duration } & \text { Predecessor } \\\hline \text { A } & 5 \text { days } & - \\\hline\mathrm { B} & 4 \text { days } & \text { A } \\\hline \mathrm { C}& 5 \text { days } & \text { A } \\\hline \mathrm { D } & 6 \text { days } & B \\\hline\mathrm { E }& 6 \text { days } & C, D \\\hline\mathrm { F} & 6 \text { days } & \mathrm { E } \\\hline\end{array}


Definitions:

Securities & Exchange Commission

A U.S. federal agency responsible for enforcing federal securities laws and regulating the securities industry, stock and options exchanges, and other electronic securities markets.

Generally Accepted Accounting Principles

A set of accounting standards and principles that guide the financial reporting process for public companies in the United States.

Financial Accounting Standards Board

An independent, nonprofit organization responsible for establishing accounting and financial reporting standards for companies and non-profit organizations in the United States.

Public Company Accounting Oversight Board

A regulatory body established by Congress to oversee the audits of public companies in order to protect investors and the public interest.

Related Questions