Examlex

Solved

Use the Project Described in the Table to Determine the Total

question 97

Multiple Choice

Use the project described in the table to determine the total resources required for this project if a worker is expected to devote half-time (four hours per day) to this project.  Activity  Duration  Predecessor  A 5 days B4 days  A C5 days  A D6 days BE6 days C,DF6 days E\begin{array} { | l | l | l |} \hline \text { Activity } & \text { Duration } & \text { Predecessor } \\\hline \text { A } & 5 \text { days } & - \\\hline B & 4 \text { days } & \text { A } \\\hline C & 5 \text { days } & \text { A } \\\hline \mathrm { D } & 6 \text { days } & B \\\hline E & 6 \text { days } & C , D \\\hline F & 6 \text { days } &\mathrm { E } \\ \hline\end{array}