A project consists of six activities (all times are given in days).Provide the range of days during which resource usage is highest and the range of days during which resource usage is lowest using a late start schedule.
 Activity  Duration (days)  Activity Cost  Predecessor K10140L864K,MM1296N6120MP14168LQ12144N\begin{array}{|l|l|l|l|}\hline \text { Activity } & \text { Duration (days) } & \text { Activity Cost } & \text { Predecessor } \\\hline\mathrm{K} & 10 & 140 & \\\hline\mathrm{L} & 8 & 64 & \mathrm{K}, \mathrm{M} \\\hline \mathrm{M} & 12 & 96 & \\\hline \mathrm{N} & 6 & 120 &\mathrm{M} \\\hline \mathrm{P} & 14 & 168 & \mathrm{L} \\\hline\mathrm{Q} & 12 & 144 & \mathrm{N} \\\hline \end{array}


Definitions:

Healthy Learning Climate

An environment within an organization that supports and encourages continuous learning, growth, and development of its members.

Organizations

Structured groups of people who come together to achieve common goals through a division of labor and a hierarchy of authority.

Formal Training Programs

Structured educational initiatives designed to enhance knowledge, skills, and competencies in a professional setting.

Effectiveness

The degree to which something is successful in producing a desired or intended result.

Related Questions