Create a Resource Loading Table and Perform Resource Leveling on the Project

question 61

Essay

Create a resource loading table and perform resource leveling on the project composed of the activities in this table.Activities listed in the table are measured in the number of eight-hour days.The maximum amount of time used per day is 16 hours.
 Activity  Time  Predecessor  A 6B1C2 A, BD4E1C,DFEEG6EH4 FJ4 FK3G,HL5J, KM5L\begin{array} { | l | l | l |} \hline\text { Activity } & \text { Time } & \text { Predecessor } \\\hline \text { A } & 6 & - \\\hline B & 1 & - \\ \hline \mathrm { C } & 2 & \mathrm {~A} , \mathrm {~B} \\\hline \mathrm { D } & 4 & - \\\hline \mathrm { E } & 1 & \mathrm { C } , \mathrm { D } \\\hline \mathrm { F } & \mathrm { E } & \mathrm { E } \\\hline \mathrm {G } & 6 & \mathrm { E } \\\hline \mathrm { H } & 4 & \mathrm {~F} \\\hline \mathrm { J } & 4 & \mathrm {~F} \\\hline \mathrm { K } & 3 & \mathbf { G } , \mathrm { H } \\\hline \mathrm { L } & 5 & \mathrm {J} , \mathrm {~K} \\\hline \mathrm { M } & \mathbf { 5 } & \mathrm { L } \\\hline\end{array}


Definitions:

External Environmental Supply

The provision of resources or inputs to an organization from its external environment, which can include materials, information, or energy.

Organizational Demand

The requirements or needs of an organization that dictate its operational, personnel, and resource requirements.

Human Resource Sources

Various origins from which organizations can recruit or acquire human capital, such as internal recruitment, job portals, and educational institutions.

Internal Workforce

The employees who are currently working within an organization, as opposed to temporary or external staff.

Related Questions