Use the Earned Value Table to Determine the Schedule Performance

question 51

Multiple Choice

Use the earned value table to determine the schedule performance index given the indicated state of the project.  Activity 5101520253035 Plan % Complete  A 8503501,200100% B 400125525100%C1,2756501,925100%D28004,5003507,65095%E6804001,08075%F1258751,00080%30012001,50045% Monthly Plan 8507501,4003,4505,1801,1752,07514,880 Monthly Act 9006501,3503,8754,7808502,000\begin{array}{|l|l|l|l|l|l|l|l|l|l|}\hline \text { Activity } & 5 & 10 & 15 & 20 & 25 & 30 & 35 & \text { Plan } & \% \text { Complete } \\\hline \text { A } & 850 & 350 & & & & & & 1,200 & 100 \% \\\hline \text { B } & & 400 & 125 & & & & & 525 & 100 \% \\\hline \text {C} & & & 1,275 & 650 & & & & 1,925 & 100 \% \\\hline \text {D} & & & & 2800 & 4,500 & 350 & & 7,650 & 95 \% \\\hline \text {E} & & & & & 680 & 400 & & 1,080 & 75 \% \\\hline \text {F} & & & & & & 125 & 875 & 1,000 & 80 \% \\\hline \text {G } & & & & & & 300 & 1200 & 1,500 & 45 \% \\\hline \text { Monthly Plan } & 850 & 750 & 1,400 & 3,450 & 5,180 & 1,175 & 2,075 & 14,880 & \\ \hline \text { Monthly Act } & 900 & 650 & 1,350 & 3,875&4,780 & 850 & 2,000 & & \\\hline\end{array}


Definitions:

Absolute Advantage

The ability of an individual, company, or country to produce a good or service at a lower cost per unit than other competitors with the same quality.

Oil

A fossil fuel in liquid form, primarily used as a source of energy and as a base for petrochemicals, extracted from underground reservoirs.

Coal

A combustible black or brownish-black sedimentary rock used primarily as a source of energy and heat.

Tariff

A tax imposed on imported goods and services to protect domestic industries or raise government revenue.

Related Questions