A department has 5 machines that each run for an average of 8.4 hours (exponential)before service is required.Service time average is 1.6 hours (exponential).
(i)While running,each machine can produce 120 pieces per hour.With one server,what is the average hourly output actually achieved?
(ii)With 2 servers,what is the probability that a machine would be served immediately when it requires service?
(iii)If machine downtime cost is $100 per hour per machine,and server time costs $30 per hour,how many servers would be optimal?
Bonds Issued
Debt securities sold by corporations or governments to raise funds, to be repaid at a future date.
Capital Lease
A contractual arrangement that transfers substantially all the benefits and risks of ownership to the lessee so that the lease is in effect a purchase of the property.
Plant Assets
Long-term tangible assets used in the operation of a business, such as buildings, machinery, and equipment.
Loss On Redemption
A financial loss experienced when redeeming bonds or securities before their maturity date for a price higher than their face value.
Q5: Multiple regression procedures permit us to extend
Q13: Quality function deployment (QFD)is based on a
Q15: The development and application of MRP is
Q20: A benefit of JIT is the flexibility
Q47: Make-to-order companies use inventory whereas make-to-stock companies
Q63: In the production planning hierarchy,scheduling is the
Q71: In waiting-line analysis,queue discipline refers to the
Q74: Safety time is sometimes used in MRP
Q74: The Theory of Constraints focuses on developing
Q156: A proactive approach to forecasts might involve