An Activity,A,has Two Succeeding Activities,B and C

question 39

Multiple Choice

An activity,A,has two succeeding activities,B and C.Given the following information,determine the latest starting time for activity A. EF B = 15,EF C = 17,LF B = 24,LF C = 27; activity times are A = 4,B = 6,C = 8.