Activity 4 in a Network Diagram Has an Optimistic Duration

question 30

Multiple Choice

Activity 4 in a network diagram has an optimistic duration estimate of 5 days,a most likely duration estimate of 7 days,and a pessimistic duration estimate of 10 days.The expected duration of Activity 4 is: