Which of the Following Are Accurate Statements Concerning MPS,MRP and Capacity

question 64

Multiple Choice

Which of the following are accurate statements concerning MPS,MRP and capacity requirements planning (CRP) ?
I.CRP is equivalent to a master production schedule (MPS) .
II.CRP is needed to determine if an MPS is feasible.
III.CRP is an input to MRP.
IV.Planned-order releases from MRP are the inputs for CRP.