You Have Run a Capacity Resource Profile on Your Shop

question 12

Essay

You have run a capacity resource profile on your shop.Products have been routed sequentially through resources A, B, C, and
C.A rope (communication) should be directed back to the start of the process, resource A, to prevent inventory from building up.Depending on the situation, a second rope can extend from the finished goods inventory location (another buffer) to resource C as described in the text.An excellent response to this question will include a diagram similar to Exhibit 23.9 and/or Exhibit 23.11.
C.A small buffer inventory should be held between resource B and resource
D.The capacity resource profile tells you that resource A is scheduled at 95 percent of capacity, resource B at 80 percent of capacity, resource C at 130 percent of capacity, and resource D at 100 percent of capacity.Assuming that the data we used to calculate the capacity resource profile are accurate, how would you employ the "drum, buffer, rope" thinking?
This concept is discussed in the text.The drum or control of the process is at the bottleneck, resource


Definitions:

Sexual Activity

Any activity that involves sexual intercourse or other sexual practices between individuals.

Cohabitating Couples

Partners who live together in a shared dwelling without being formally married.

Married Couples

Two individuals joined in marriage, recognized legally, socially, or religiously, committed to a shared life together.

Entering Marriage

The act of beginning a legally and socially recognized union between two people, marking a significant life change.

Related Questions