Assume You Are Sequencing Jobs Using Johnson's Rule

question 99

Multiple Choice

Assume you are sequencing jobs using Johnson's rule. A particular job requires 7 hours to assemble and then is followed by 8 hours in the painting department. Which of the following is where you would schedule this job?