question 61

Multiple Choice

Here are the data for a time-cost CPM scheduling analysis.The time is in days and the costs include both direct and indirect costs. Here are the data for a time-cost CPM scheduling analysis.The time is in days and the costs include both direct and indirect costs.   If you crash this project to reduce the total time by four days, what is the total time of the project and total cost? A) Total time is 10 days, total cost is $2,500. B) Total time is 9 days, total cost is $2,300. C) Total time is 8 days, total cost is $2,750. D) Total time is 8 days, total cost is $1,850. E) Total time is 9 days, total cost is $2,350. If you crash this project to reduce the total time by four days, what is the total time of the project and total cost?


Definitions:

Topic Sentence

A sentence that expresses the main idea of the paragraph in which it occurs.

Easy-To-Read Messages

Texts or communications designed to be easily understood, often using simple language and formatting to improve accessibility.

Eliminating Alternatives

The process of systematically removing options to narrow down choices in decision-making or problem-solving.

Headings

Titles or captions used to organize and label sections of text for easier navigation and understanding.

Related Questions