You Have Collected the Data for a Time-Cost CPM Scheduling

question 35

Multiple Choice

You have collected the data for a time-cost CPM scheduling model analysis.The time is in days and the project "direct costs" are given here. You have collected the data for a time-cost CPM scheduling model analysis.The time is in days and the project  direct costs  are given here.   The indirect costs for the project are determined on a daily duration basis.If the project lasts 16 days, the total indirect costs are $400; 15 days, they will be $250; 14 days, they will be $200; and 13 days, they will be $100.At what day do we achieve the lowest total project cost (i.e., direct plus indirect costs) ? A)  16 days B)  15 days C)  14 days D)  13 days E)  12 days The indirect costs for the project are determined on a daily duration basis.If the project lasts 16 days, the total indirect costs are $400; 15 days, they will be $250; 14 days, they will be $200; and 13 days, they will be $100.At what day do we achieve the lowest total project cost (i.e., direct plus indirect costs) ?


Definitions:

Investing Activities

Investing activities include transactions involving the acquisition or disposal of long-term assets and investments, which are reflected in the cash flow statement.

Purchase of Land

An accounting transaction involving the acquisition of land, classified as a non-current asset on the balance sheet.

Significant Noncash

Transactions or activities that have a major impact on a company's financial position but do not involve a direct exchange of cash.

Preferred Shares

A class of stock that provides owners with a fixed dividend ahead of the company's common shares and with priority over common shares in asset liquidation.

Related Questions