The process of planning business actions in the near future and expressing them as formal plans of action is called:


Definitions:

What-If Calculations

Analytical processes used to explore the outcomes of different scenarios or decisions based on varying inputs or variables.

Gantt Chart

A visual project management tool that displays tasks or activities against time.

PERT Chart

is a project management tool used to schedule, organize, and coordinate tasks within a project, standing for Program Evaluation and Review Technique.

Critical Path Method

A project management technique that identifies the longest sequence of dependent tasks and calculates the shortest possible project duration.