The Correct Opportunity Cost for a Project Is Determined to Be

question 62

Multiple Choice

The correct opportunity cost for a project is determined to be 15% and the project is expected to generate $1 million in cash flows at the end of the next 4 years after an initial outlay of $3 million. Based on this information, the project would plot: